AD 2013-26-01
Applicability
| Type | Manufacturer | Model | Details |
|---|---|---|---|
| engine | CFM | International S | Airworthiness Directives; CFM International S.A. Turbofan Engines |
Unsafe Condition
Total loss of engine oil from CFM56 series turbofan engines while in flight, caused by unsecured handcranking pad covers.
AI-generated summary from the source AD text. Verify against the official source before acting.
Required Actions
An independent inspection is required to verify re-installation of the handcranking pad cover after removal for maintenance. Operators may also insert an Independent Inspection requirement in their aircraft Continuous Airworthiness Maintenance Program (CAMP).
AI-generated summary from the source AD text. Verify against the official source before acting.
Compliance Time
Within 35 days of publication in the Federal Register.
AI-generated summary from the source AD text. Verify against the official source before acting.
Affected Aircraft
All CFM International S.A. CFM56-3 and CFM56-7B series turbofan engines with certain accessory gearboxes (AGBs) not equipped with a handcranking pad oil dynamic seal assembly.
AI-generated summary from the source AD text. Verify against the official source before acting.
Federal Register Abstract
We are adopting a new airworthiness directive (AD) for all CFM International (CFM) S.A. CFM56-3 and CFM56-7B series turbofan engines with certain accessory gearboxes (AGBs) not equipped with a handcranking pad "oil dynamic seal" assembly. This AD was prompted by 42 events of total loss of engine oil from CFM56 series turbofan engines while in flight. This AD requires an independent inspection to verify re-installation of the handcranking pad cover after removal of the pad cover for maintenance until installation of a handcranking pad oil dynamic seal assembly. We are issuing this AD to prevent loss of engine oil while in flight, which could result in engine failure, loss of thrust control, and damage to the airplane.
Applicability Source Text
Show captured applicability text from the source AD
(c) Applicability
This AD applies to CFM International S.A. CFM56-3 series and
CFM56-7B series turbofan engines equipped with the following
accessory gearbox (AGB) part numbers (P/Ns):
(1) For CFM56-3 engines: 335-300-103-0, 335-300-105-0, 335-300-
106-0, 335-300-107-0, 335-300-108-0, 335-300-109-0, or 335-300-110-
0.
(2) For CFM56-7B engines (except CFM56-7B27A, CFM56-7B27A/3, and
CFM56-7B27AE engines): 340-046-503-0, 340-046-504-0, or 340-046-505-
0.
(3) For CFM56-7B27A, CFM56-7B27A/3, and CFM56-7B27AE engines:
340-188-601-0 or 340-188-603-0.
Document Text
Show stored source text (verify against official source)
[Federal Register Volume 78, Number 250 (Monday, December 30, 2013)]
[Rules and Regulations]
[Pages 79295-79298]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2013-30862]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
14 CFR Part 39
[Docket No. FAA-2013-0407; Directorate Identifier 2012-NE-22-AD;
Amendment 39-17710; AD 2013-26-01]
RIN 2120-AA64
Airworthiness Directives; CFM International S.A. Turbofan Engines
AGENCY: Federal Aviation Administration (FAA), DOT.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: We are adopting a new airworthiness directive (AD) for all CFM
International (CFM) S.A. CFM56-3 and CFM56-7B series turbofan engines
with certain accessory gearboxes (AGBs) not equipped with a
handcranking pad ``oil dynamic seal'' assembly. This AD was prompted by
42 events of total loss of engine oil from CFM56 series turbofan
engines while in flight. This AD requires an independent inspection to
verify re-installation of the handcranking pad cover after removal of
the pad cover for maintenance until installation of a handcranking pad
oil dynamic seal assembly. We are issuing this AD to prevent loss of
engine oil while in flight, which could result in engine failure, loss
of thrust control, and damage to the airplane.
DATES: This AD is effective February 3, 2014.
ADDRESSES: For service information identified in this AD, contact CFM
International Inc., Aviation Operations Center, 1 Neumann Way, M/D Room
285, Cincinnati, OH 45125; phone: 877-432-3272; fax: 877-432-3329;
email: <a href="/cdn-cgi/l/email-protection#e582808480cb848a86a58280cb868a88"><span class="__cf_email__" data-cfemail="5b3c3e3a3e753a34381b3c3e75383436">[email protected]</span></a>. You may view this service information at the
FAA, Engine & Propeller Directorate, 12 New England Executive Park,
Burlington, MA. For information on the availability of this material at
the FAA, call 781-238-7125.
Examining the AD Docket
You may examine the AD docket on the Internet at <a href="http://www.regulations.gov">http://www.regulations.gov</a> by searching for and locating Docket No. FAA-2013-
0407; or in person at the Docket Management Facility between 9 a.m. and
5 p.m., Monday through Friday, except Federal holidays. The AD docket
contains this AD, the regulatory evaluation, any comments received, and
other information. The address for the Docket Office (phone: 800-647-
5527) is Document Management Facility, U.S. Department of
Transportation, Docket Operations, M-30, West Building Ground Floor,
Room W12-140, 1200 New Jersey Avenue SE., Washington, DC 20590.
FOR FURTHER INFORMATION CONTACT: Antonio Cancelliere, Aerospace
Engineer, Engine Certification Office, FAA, Engine & Propeller
Directorate, 12 New England Executive Park, Burlington, Massachusetts,
01803; phone: 781-238-7751; fax: 781-238-7199; email:
<a href="/cdn-cgi/l/email-protection#ddbcb3a9b2b3b4b2f3bebcb3beb8b1b1b4b8afb89dbbbcbcf3bab2ab"><span class="__cf_email__" data-cfemail="ed8c839982838482c38e8c838e88818184889f88ad8b8c8cc38a829b">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION:
Discussion
We issued a notice of proposed rulemaking (NPRM) to amend 14 CFR
part 39 to include an AD that would apply to the specified products.
The NPRM published in the Federal Register on June 10, 2013 (78 FR
34605). The NPRM proposed to require an independent inspection to
verify re-installation of the handcranking pad
[[Page 79296]]
cover after removal of the pad cover for maintenance until installation
of a handcranking pad oil dynamic seal assembly.
Comments
We gave the public the opportunity to participate in developing
this AD. The following presents the comments received on the proposal
and the FAA's response to each comment.
Request To Make Optional Terminating Action Mandatory
The National Transportation Safety Board comments that the FAA
should make the installation of an oil dynamic seal assembly a
mandatory, rather than an optional, terminating action, as has the
European Aviation Safety Agency (EASA) and the Civil Aviation
Administration of China.
The FAA agrees that the loss of engine oil from unsecured
handcranking pad covers can be addressed with the introduction of a
dynamic seal. The FAA has structured its approach to achieving that
goal, however, through a combination of inspections and part
replacement, which allows each affected operator to manage its own
maintenance schedule. The FAA believes that this approach will not have
as great an economic effect on the affected operators as mandating a
part replacement. The FAA also finds that the level of safety achieved
with its approach to this unsafe condition is acceptable, and believes
that operators will eventually incorporate the dynamic seal to
terminate the required inspections.
Request To Revise Optional Terminating Action
American Airlines (AAL) requested that we revise paragraph (g) of
the AD (the Terminating Action paragraph) to minimize the effects of
differences in the AGB disassembly and assembly procedures between
those specified in the engine shop manual and current or subsequent
service bulletins. AAL noted that this method of specifying the
terminating action would preclude the need for Alternative Method of
Compliance (AMOC) requests.
We agree in part. We revised the Terminating Action paragraph by
removing the requirement to follow specific service bulletins (SBs).
Guidance on CFM CFM56 SBs and engine manual can now be found in the
Related Information section of this AD.
Request To Include FAA-Approved Maintenance Program in Compliance
Airlines for America asked that we include in paragraph (f) of this
AD, a time period in which an approved maintenance program must be
revised to include an Independent Inspection. Airlines for America also
asked that we clarify that documentation for each inspection on every
airplane need not be made if relying on the insertion of an Independent
Inspection in the aircraft Continuous Airworthiness Maintenance Program
(CAMP).
We agree in part, and have made paragraphs (f)(1) and (f)(2) of
this AD disjunctive in order to clarify that either an Independent
Inspection is required after each maintenance involving the
handcranking pad cover or that operators insert an Independent
Inspection requirement in their aircraft CAMP. We do point out that if
an operator relies on paragraph (f)(1) of this AD, a maintenance record
entry is required to record compliance with this AD after each time the
handcranking pad cover is removed and re-installed. If an operator
relies on paragraph (f)(2) of this AD however, only one record entry is
required to document that the CAMP has been modified as required. After
the CAMP has been modified, the operator need only document actions as
required by the CAMP.
We have not, however, added a time period within which operators
must make a change to their CAMP. This AD itself states that it will
become effective 35 days after publication in the Federal Register.
After that date, operators must comply with either paragraph (f)(1),
(f)(2), or (g) of this AD.
Request To Clarify Inspection Options
Delta Airlines (Delta) requested that we clarify that both apparent
options--an independent inspection or addition of the inspection as a
Required Inspection Item into the operator's approved CAMP--in
compliance with paragraph (f) of this AD are indeed options for meeting
the requirements of this AD.
We agree that further clarification was needed. As explained with
the response to the Airlines for America comment, we have made
paragraphs (f)(1) and (f)(2) of this AD disjunctive to clarify that an
operator either perform an Independent Inspection each time the
handcranking pad cover is removed and re-installed, or insert in its
aircraft CAMP a requirement for an Independent Inspection.
Request To Delay Issuance of This AD
Delta requested that we delay issuance of this AD until CFM issues
revisions to CFM SB CFM56-7B S/B 72-0564, Revision 3, dated May 25,
2011, and CFM SB CFM56-7B S/B 27-0879, Revision 1, dated April 12,
2012. Delay in publication of this AD would minimize the burden of AMOC
requests on operators, CFM, and the FAA. It would also allow CFM to
modify these SBs to correct tooling references and to modify
impingement test requirements.
We partially agree. We agree that we need not mandate use of
specific SB versions to accomplish the terminating action. We have
therefore, removed those SB references from paragraph (g) of this AD
and moved those references to paragraph (j), Related Information, of
this AD. This will eliminate the need for requests for AMOCs should the
manufacturer modify its SBs. Accordingly, we need not delay issuance of
this AD until any particular SB version is published.
Request To Allow Acceptable Maintenance Procedures To Install Seal
Delta requested that we allow operators or maintenance facilities
to install oil dynamic seal assemblies using the SBs referenced in the
NPRM (78 FR 34605, June 10, 2013) along with other acceptable
maintenance procedures rather than mandating that all work be performed
in accordance with the referenced SBs.
We agree. We moved the references to the SBs from the compliance
section of this AD to the Related Information section of this AD.
Request To Define Compliance Time
Delta asked that we specifically define the compliance time in
which operators have after the effective date of this AD to put the
inspection program in place.
We disagree. As stated earlier, this AD will become effective as
indicated in the DATES section. As of that date, operators must comply
with this AD by either following paragraph (f)(1) of this AD for each
time maintenance is performed to remove and re-install the handcranking
pad cover, or (f)(2) of this AD to insert an Independent Inspection
requirement in their aircraft CAMP, or (g) of this AD by replacing the
AGB that incorporates an oil dynamic seal assembly. No further
compliance time need be allowed. We did not change this AD.
Request To Harmonize With EASA AD 2012-0209
RyanAir requested that we harmonize differences between the NPRM
(78 FR 34605, June 10, 2013) and EASA AD 2012-0209, dated October 8,
2012. RyanAir identified differences between the EASA AD and the NPRM
in the areas of applicability, terminating action, service information,
and compliance language.
We disagree. We believe that references in the Applicability
section
[[Page 79297]]
of this AD to specific AGB part numbers not equipped with the oil
dynamic seal assembly will avoid the need to revise this AD in the
future should additional approved AGBs be available for installation.
We did not change this AD.
Support for This AD
The Boeing Company and United Airlines support this AD as proposed
(78 FR 34605, June 10, 2013).
Conclusion
We reviewed the relevant data, considered the comments received,
and determined that air safety and the public interest require adopting
this AD with the changes described previously.
We also determined that these changes will not increase the
economic burden on any operator or increase the scope of this AD.
Costs of Compliance
We estimate that this AD will affect 2,702 CFM56-3 and CFM56-7B
engines installed on airplanes of U.S. registry. We also estimate that
it will take about 1 hour to perform the independent inspection
required by this AD. The average labor rate is $85 per hour. We
estimate that normal maintenance will require the AGB handcranking pad
cover to be removed every 1,300 flights cycles. Based on an average use
of these model engines of approximately 6,000,000 flight cycles per
year, we estimate that an independent inspection would be required
about 4,615 times per year. Therefore, assuming that an operator does
not already have an Independent Inspection of the AGB handcranking pad
cover in its approved aircraft maintenance program, we estimate the
cost of this AD for U.S. operators to be $392,275.
Authority for This Rulemaking
Title 49 of the United States Code specifies the FAA's authority to
issue rules on aviation safety. Subtitle I, section 106, describes the
authority of the FAA Administrator. Subtitle VII: Aviation Programs,
describes in more detail the scope of the Agency's authority.
We are issuing this rulemaking under the authority described in
Subtitle VII, Part A, Subpart III, Section 44701: ``General
requirements.'' Under that section, Congress charges the FAA with
promoting safe flight of civil aircraft in air commerce by prescribing
regulations for practices, methods, and procedures the Administrator
finds necessary for safety in air commerce. This regulation is within
the scope of that authority because it addresses an unsafe condition
that is likely to exist or develop on products identified in this
rulemaking action.
Regulatory Findings
This AD will not have federalism implications under Executive Order
13132. This AD will not have a substantial direct effect on the States,
on the relationship between the national government and the States, or
on the distribution of power and responsibilities among the various
levels of government.
For the reasons discussed above, I certify that this AD:
(1) Is not a ``significant regulatory action'' under Executive
Order 12866,
(2) Is not a ``significant rule'' under DOT Regulatory Policies and
Procedures (44 FR 11034, February 26, 1979),
(3) Will not affect intrastate aviation in Alaska to the extent
that it justifies making a regulatory distinction, and
(4) Will not have a significant economic impact, positive or
negative, on a substantial number of small entities under the criteria
of the Regulatory Flexibility Act.
List of Subjects in 14 CFR Part 39
Air transportation, Aircraft, Aviation safety, Incorporation by
reference, Safety.
Adoption of the Amendment
Accordingly, under the authority delegated to me by the
Administrator, the FAA amends 14 CFR part 39 as follows:
PART 39--AIRWORTHINESS DIRECTIVES
0
1. The authority citation for part 39 continues to read as follows:
Authority: 49 U.S.C. 106(g), 40113, 44701.
Sec. 39.13 [Amended]
0
2. The FAA amends Sec. 39.13 by adding the following new airworthiness
directive (AD):
2013-26-01 CFM International S.A.: Amendment 39-17710; Docket No.
FAA-2013-0407; Directorate Identifier 2012-NE-22-AD.
(a) Effective Date
This AD is effective February 3, 2014.
(b) Affected ADs
None.
(c) Applicability
This AD applies to CFM International S.A. CFM56-3 series and
CFM56-7B series turbofan engines equipped with the following
accessory gearbox (AGB) part numbers (P/Ns):
(1) For CFM56-3 engines: 335-300-103-0, 335-300-105-0, 335-300-
106-0, 335-300-107-0, 335-300-108-0, 335-300-109-0, or 335-300-110-
0.
(2) For CFM56-7B engines (except CFM56-7B27A, CFM56-7B27A/3, and
CFM56-7B27AE engines): 340-046-503-0, 340-046-504-0, or 340-046-505-
0.
(3) For CFM56-7B27A, CFM56-7B27A/3, and CFM56-7B27AE engines:
340-188-601-0 or 340-188-603-0.
(d) Unsafe Condition
This AD was prompted by 42 events of total loss of engine oil
while in flight. We are issuing this AD to prevent loss of engine
oil while in flight, which could result in engine failure, loss of
thrust control, and damage to the airplane.
(e) Compliance
Unless already done, do the actions in paragraphs (f) or (g) of
this AD.
(f) Inspection of the AGB Handcranking Pad Cover
(1) Perform an Independent Inspection to verify re-installation
of the AGB handcranking pad cover after any maintenance that
involves the removal and re-installation of the AGB handcranking
cover, or
(2) Insert an Independent Inspection as a required inspection
item in the approved continuous airworthiness maintenance program
for the aircraft.
(g) Optional Terminating Action
As an optional terminating action to the inspection requirement
of paragraph (f) of this AD, install an AGB that is not listed in
paragraph (c) of this AD that incorporates the oil dynamic seal
assembly.
(h) Definition
For the purpose of this AD, an Independent Inspection means a
second inspection by a qualified individual who was not involved in
the original re-installation of the AGB handcranking pad cover
following maintenance to confirm that the cover is installed
correctly.
(i) Alternative Methods of Compliance (AMOCs)
The Manager, Engine Certification Office, FAA, may approve AMOCs
for this AD. Use the procedures found in 14 CFR 39.19 to make your
request.
(j) Related Information
(1) For more information about this AD, contact Antonio
Cancelliere, Aerospace Engineer, Engine Certification Office, FAA,
Engine & Propeller Directorate, 12 New England Executive Park,
Burlington, Massachusetts, 01803; phone: 781-238-7751; fax: 781-238-
7199; email: <a href="/cdn-cgi/l/email-protection#e5848b918a8b8c8acb86848b868089898c809780a5838484cb828a93"><span class="__cf_email__" data-cfemail="1b7a756f7475727435787a75787e7777727e697e5b7d7a7a357c746d">[email protected]</span></a>.
(2) CFM International S.A. Service Bulletin (SB) No. CFM56-7B S/
B 72-0564, Revision 3, dated May 25, 2011, and SB No. CFM56-7B S/B
27-0879, Revision 1, dated April 12, 2012, which are not
incorporated by reference in this AD, provide guidance on obtaining
an AGB that incorporates an oil dynamic seal assembly. The CFM56
engine manuals, which are also not incorporated by reference in this
AD, include instructions on assembling and disassembling the AGB.
(3) For service information identified in this AD, contact CFM
International Inc.,
[[Page 79298]]
Aviation Operations Center, 1 Neumann Way, M/D Room 285, Cincinnati,
OH 45125; phone: 877-432-3272; fax: 877-432-3329; email:
<a href="/cdn-cgi/l/email-protection#e88f8d898dc689878ba88f8dc68b8785"><span class="__cf_email__" data-cfemail="deb9bbbfbbf0bfb1bd9eb9bbf0bdb1b3">[email protected]</span></a>.
(4) You may view this service information at the FAA, Engine &
Propeller Directorate, 12 New England Executive Park, Burlington,
MA. For information on the availability of this material at the FAA,
call 781-238-7125.
(k) Material Incorporated by Reference
None.
Issued in Burlington, Massachusetts, on December 16, 2013.
Frank P. Paskiewicz,
Acting Director, Aircraft Certification Service.
[FR Doc. 2013-30862 Filed 12-27-13; 8:45 am]
BILLING CODE 4910-13-P
Source: Official FAA Source ↗
Retrieved: Apr 4, 2026
Rights: U.S. Government Public Domain
This site is not affiliated with or endorsed by the FAA. Always verify with official sources.